HomeMy WebLinkAbout~Master - Completion of Power Plant Unit No. 8 Stack Repair Project RESOLUTION NO. 12-304
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR POWER PLANT UNIT NO. 8 STACK REPAIR
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Power Plant Unit No. 8 Stack Repair for the City of Ames,Iowa,in accordance with a contract dated
September 14,2010,by and between the City of Ames,Iowa,and Gerard Chimney Company of St.
Louis, Missouri.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Power Plant Unit No. 8 Stack Repair has been fully
completed by the Contractor in accordance with the terms of the contract and is hereby
accepted and approved.
Section 2. The total cost of the contract is $217,816.26.
Section 3. The amount due Gerard Chimney Company of St. Louis,Missouri,is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 12`h day of June, 2012.
lidA.., At-loto to/. ca-4"C"04�—�
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Davis
Seconded by: Szopinksi
Voting aye: Davis, Goodman, Larson, Orazem, Szopinski, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 12'h day of June, 2012.