Ladies and Gentlemen:
I hereby certify that the sanitary sewer, watermain, and storm sewer in Aspen Business
Park has been completed in an acceptable manner by KRI Company of Ames, Iowa, and has
been inspected by the Engineering Division of the Public Works Department of the City
of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
See Attachment
Total $219,693.30
Sincerely,
Paul D.Wiegand,P.E.
Public Works Director
Approved by:
/ gi-elL Jul—
T. Robert Kindred, Assistant City Manager
PDW/kg
c: City Clerk, Finance, Contractor, PW Admin.Asst. , Construction Supervisor
"�.f;7
r
ti
0 Description Unit Ouantity Price Total
2 Sanitary manhole ea. 6.0 1,225.00 7,350.00
3 8" sanitary sewer l.f. 1333.0 32.00 42,656.00
6 Connect to exist sewer ea. 1.0 350.00 350.00
7 8" watermain l.f. 1861.0 19.55 36,382.55
8 Connect to exist 8" water ea. 1.0 575.00 575.00
9 Connect to exist 12" water ea. 1.0 875.00 875.00
10 Bore 15" casing at 16th l.f. 40.0 140.00 5,600.00
11 8" water valve and box ea. 7.0 525.00 3,675.00
12 fire hydrant w/valve ea. 6.0 700.00 4,200.00
13 RA-3 intake ea. 11.0 950.00 10,450.00
14 RA-5 intake ea. 2.0 1,150.00 2,300.00
15 12" storm sewer l.f. 32.0 30.30 969.60
16 15" storm sewer l.f. 171.0 32.25 5,514.75
17 18" storm sewer l.f. 159.0 33.70 5,358.30
18 24" storm sewer l.f. 260.0 38.70 10,062.00
19 30" storm sewer l.f. 568.0 45.05 25,588.40
20 36" storm sewer l.f. 380.0 53.90 20,482.00
21 54 x 36 arch l.f. 291.0 91.05 26,495.55
22 54 x 36 arch apron ea. 1.0 1,045.00 1,045.00
23 18" on 24" tee ea. 1.0 400.00 400.00
25 Concrete cap 30" ea. 1.0 85.00 85.00
27 Outlet structure l.s. 1.0 500.00 500.00
28 Outlet rip-rap ton 15.49 35.00 542.15
34 Storm sewer MH ea. 1.0 1,250.00 1,250.00
35 RA-3 top sections ea. 11.0 415.00 4,565.00
36 RA-5 top sections ea. 2.0 586.00 1,172.00
38 8 x 8 x 8 cross ea. 2.0 350.00 700.00
39 8 x 8 x 8 tee ea. 2..0 275.00 550.00