HomeMy WebLinkAbout~Master - Completion of ISU Vet Med Substation 15 k-V Metalclad Switchgear RESOLUTION NO. 11-310
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR ISU VET MED SUBSTATION 15-kV METALCLAD SWITCHGEAR
FOR THE CITY OF AMES, IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
ISU Veterinary(Vet)Medicine(Med)Substation 15-kV Metalclad Switchgear for the City of Ames,
Iowa,in accordance with a contract dated August 24,2010,by and between the City of Ames,Iowa,
and Pedersen Power Products of Omaha,Nebraska.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the ISU Veterinary(Vet) Medicine (Med) Substation
15-kV Metalclad Switchgear has been fully completed by the Contractor in accordance
with the terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $568,055.29.
Section 3. The amount due Pedersen Power Products of Omaha, Nebraska, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 28'day of June, 2011.
oel-
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Mahayni
Seconded by: Davis
Voting aye: Davis, Goodman, Larson, Mahayni, Orazem, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 28t''day of June, 2011.