HomeMy WebLinkAbout~Master - Change Order for Boiler Retube engineering services contract RESOLUTION NO. 11-047
RESOLUTION APPROVING CHANGE ORDER NO. 4
FOR BOILER RETUBE ENGINEERING SERVICES CONTRACT
FOR THE CITY OF AMES,IOWA
WHEREAS,Unit No. 8 at the Power Plant is a 65-megawatt electric generating unit fired by coal
and refuse derived fuel (RDF) that was placed into service in 1982; and,
WHEREAS, in recent years, Unit 8's boiler has been plagued with tube failures in the lower
waterwall and in the superheater sections of the boiler,resulting in numerous forced outages and Unit down
time; and,
WHEREAS, a plan is in place to address the tube failure issues pertaining to the lower waterwall
section of the boiler, and,
WHEREAS,a plan also needs to be developed to address the tube failure issues of the superheater
section of Unit No. 8 boiler, and the first step is to engage an engineering firm to assist the City in
development of a strategy for repair; and,
WHEREAS,in 2007,the City contracted with Utility Engineering of Minneapolis,Minnesota,(now
known as Zachry Engineering) for engineering services to prepare a scope of work and specifications for
Unit No. 8's boiler lower waterwall tube repair/replacement project; ;and,
t
WHEREAS,this was referred to as Phase I,and Phase II,as an option for Zachry Engineering,had
essentially the same scope of engineering work as Phase I,except that it would address the superheater tube
failure problems of Unit No. 8 boiler; and,
WHEREAS,the original purchase order with Zachry Engineering for Phase I work was for a not-
to-exceed amount of$80,000,but subsequently,three change orders have been made to that contract;and,
WHEREAS,staff proposes that a contract change order be issued to Zachry Engineering to perform
engineering services in developing a scope of work and material and installation specifications for the
repair/replacement of the superheater for Unit No. 8 boiler; and,
WHEREAS,the engineering services as described will be referred to as Phase II,and this Change
Order No.4 will allow Zachry Engineering to complete the engineering for this phase in an amount not to
exceed$49,500.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa, that
Change Order No. 4 in an amount not to exceed $49,500 with Zachry Engineering of Minneapolis,
Minnesota, for Phase II of the boiler retube engineering services contract is hereby approved.
ADOPTED THIS 8`''day of February, 2011.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Davis
Seconded by: Larson
Voting aye: Davis, Goodman, Larson, Mahayni, Orazem
Voting nay: None Absent: Wacha
Resolution declared adopted and signed by the Mayor this 8`'day of February, 2011.