HomeMy WebLinkAbout~Master - Completion of Storm Sewer Outlet Erosion Control Project - College Creek RESOLUTION NO. 11-014
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR 2008/09, 2009/10,AND 2010/11 STORM SEWER OUTLET
EROSION CONTROL PROJECTS (COLLEGE CREED
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2008/09, 2009/10, and 2010/11 Storm Sewer Outlet Erosion Control Projects (College Creek) for
the City of Ames,Iowa,in accordance with a contract dated June 22,2010,by and between the City
of Ames,Iowa, and Sunram Construction, Inc., of Corcoran, Minnesota.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2008/09,2009/10,and 2010/11 Storm Sewer Outlet
Erosion Control Projects(College Creek)has been fully completed by the Contractor in
accordance with the terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $348,504.61.
Section 3. The amount due Sunram Construction, Inc., of Corcoran, Minnesota, is
hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 1 lth day of January, 2011.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Davis
Seconded by: Wacha
Voting aye: Davis, Goodman, Larson, Orazem, Wacha
Voting nay: None Absent: Mahayni
Resolution declared adopted and signed by the Mayor this 1 lth day of January, 2011.