RESOLUTION NO. 11-012
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR STANGE ROAD SUBSTATION TO AMES POWER PLANT
161/69 kV TRANSMISSION LINE
FOR THE CITY OF AMES,IOWA
WHEREAS,the Electric Department has filed a certificate of completion for the Stange Road
Substation to Ames Power Plant 161/69 kV Transmission Line for the City of Ames, Iowa, in
accordance with a contract dated January 13, 2009, by and between the City of Ames, Iowa, and
Hooper Corporation of Madison, Wisconsin..
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Stange Road Substation to Ames Power Plant
161/69 kV Transmission Line has been fully completed by the Contractor in accordance
with the terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $3,652,770.54.
Section 3. The amount due Hooper Corporation of Madison, Wisconsin, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 1Ith day of January, 2011.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Davis
Seconded by: Wacha
Voting aye: Davis, Goodman, Larson, Orazem, Wacha
Voting nay: None Absent: Mahayni
Resolution declared adopted and signed by the Mayor this 1 lth day of January, 2011.