HomeMy WebLinkAbout~Master - Completion of RRP Recyclables Building/Storage Area - Parking Lot RESOLUTION NO. 10-524
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR RESOURCE RECOVERY RECYCLABLES BUILDING AND STORAGE AREA—
PHASE I (PARKING LOT)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
Resource Recovery Recyclables Building and Storage Area—Phase I(Parking Lot) for the City of
Ames, Iowa, in accordance with a contract dated June 22,2010,by and between the City of Ames,
Iowa, and Absolute Concrete Construction of Slater, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Resource Recovery Recyclables Building and
Storage Area — Phase I (Parking Lot) has been fully completed by the Contractor in
accordance with the terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $62,678.50.
Section 3. The amount due Absolute Concrete Construction of Slater, Iowa, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 9th day of November, 2010.
`4 Vim' �lv
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Mahayni
Seconded by: Wacha
Voting aye: Davis, Goodman, Larson, Mahayni, Orazem, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 9th day of November, 2010.