HomeMy WebLinkAbout~Master - Change Order for Concrete Crushing Contract RESOLUTION NO. 10-522
RESOLUTION APPROVING CHANGE ORDER FOR
CONCRETE CRUSHING CONTRACT
FOR THE CITY OF AMES
WHEREAS, the City of Ames Public Works Department entered into a contract for concrete
crushing after receiving competitive quotes in the amount of$46,000; and,
WHEREAS,the crushing contractor s makes specific types of granular material that can be used
for a variety of projects in Public Works and provides a significant cost savings over buying virgin
material; and,
WHEREAS,the contractor is near the amount of the contract and Public Works still has a large
amount of material that could be crushed; and,
WHEREAS, due to the quality of the product being produced and the potential cost savings
from the product, staff would like to increase the contract by$15,000 to crush more material; ;and,
WHEREAS,this would bring the total contract to$61,000,and since this exceeds$50,000,the
Council is required to approve the change order to allow the work to continue.
NOW,THEREFORE,BE IT RESOLVED by the City Council of the City of Ames,Iowa,that
the Change Order with Reilly Construction Company,Inc.,in an amount not to exceed$15,000 for the
Concrete Crushing Contract is hereby approved, for a total contract amount of$61,000.
ADOPTED THIS 9`' day of November, 2010.
`-4 Jdkvfto
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Mahayni
Seconded by: Wacha
Voting aye: Davis, Goodman, Mahayni, Larson, Orazem, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 91h day of November, 2010.