HomeMy WebLinkAbout~Master - Completion of 2008/09 Neighborhood Curb Replacement Program RESOLUTION NO. 10-432
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR 2008/09 NEIGHBORHOOD CURB REPLACEMENT PROGRAM
(12TH AND HARDING)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2008/09 Neighborhood Curb Replacement Program(12t'and Harding)for the City of Ames,Iowa,
in accordance with a contract dated May 27, 2008,by and between the City of Ames,Iowa,and TK
Concrete, Inc., of Pella, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2008/09 Neighborhood Curb Replacement Program
(12t1i and Harding) has been fully completed by the Contractor in accordance with the
terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $122,999.13.
Section 3. The amount due TK Concrete,Inc., of Pella,Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 14th day of September, 2010.
`4 Vim' �lv
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Mahayni
Seconded by: Wacha
Voting aye: Davis, Goodman, Larson, Mahayni, Orazem, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 14' day of September, 2010.