HomeMy WebLinkAbout~Master - Contract for Part 1: GT-1 Engine Overhaul/Swap RESOLUTION NO. 10-366
RESOLUTION APPROVING ENGINEERING SERVICES CONTRACT
FOR PART 1: GT-1 ENGINE OVERHAUL/SWAP
FOR THE CITY OF AMES
WHEREAS,there are three upcoming projects which affect the Electric Services Department's Gas
Turbine located at the Dayton Substation; and,
WHEREAS, staff consolidated the required engineering services portions of these projects for the
Power Plant into a single Request for Proposal (RFP); and,
WHEREAS,this will allow staff to procure these services more efficiently since each project requires
similar qualifications from engineering firms; and,
WHEREAS, on June 17, 2010, the RFP document was issued to nine firms for proposals, and staff
received competitive proposals from three firms; and,
WHEREAS, these proposals were then sent to a committee for evaluation, and committee members
independently evaluated and scored all three of the proposals in two separate steps; and,
WHEREAS,Project 1,Engineering for the GT-1 Engine Overhaul/Swap,is for services to perform an
engine inspection and feasibility study leading to a commendation for either an engine overhaul or engine
replacement at GT-1; and,
WHEREAS,the study will consider such things as: 1)availability of in-kind engines for swap;2)cost
comparison to make the swap which includes the removal of the existing engine and installation of the rebuilt
swap engine versus an on-site overhaul with new or rebuilt parts as required;and,3)outage time to make a GT-
1 swap and overhaul project time frame versus outage time and overall project time frame for a complete engine
overhaul; and,
WHEREAS,staff recommends that a contract be awarded to Black&Veatch of Kansas City,Missouri,
in an amount not to exceed$50,000 for the above-mentioned work; and,
WHEREAS,the approved FY 2010/11 CIP includes $650,000 for the GT-1 Engine Overhaul/Swap.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa, that the
engineering services contract for Part 1: GT-1 Engine Overhaul/Swap with Black&Veatch of Kansas City,
Missouri,in an amount not to exceed$50,000 is hereby approved.
ADOPTED THIS 10'b day of August,2010.
C:�?. Lxd& A. ,V.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Mahayni
Seconded by: Davis
Voting aye: Davis, Goodman,Mahayni, Larson, Orazem,Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 10"'day of August, 2010.