HomeMy WebLinkAbout~Master - Partial completion for Furman Aquatic Center RESOLUTION NO. 10-168
RESOLUTION APPROVING PARTIAL ACCEPTANCE OF COMPLETION AND
RELEASE OF RETAINED FUNDS FOR FURMAN AQUATIC CENTER
FOR THE CITY OF AMES
WHEREAS, the City's consulting architectural firm for the Furman Aquatic Center, RDG
Planning and Design, completed a final walk-through of the Aquatic Center and provided the City
with a Certificate of Completion; and,
WHEREAS, during its walk-through, RDG developed a"punch list" of items that need to
be addressed this spring; and,
WHEREAS, based on the Certificate of Completion, Sande Construction has requested an
early partial release of retained funds; and,
WHEREAS,as called for in the Iowa Code,provisions for earlyrelease of funds is required,
and the amount of partial release equates to $277,596; and,
WHEREAS,upon"final acceptance"of the project later this spring,the City will pay Sande
Construction the remaining balance.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that partial acceptance of the completion of the Furman Aquatic Center is hereby approved,and the
release of retained funds to Sande Construction in the amount of$277,596 is hereby authorized.
ADOPTED THIS 27`h day of April, 2010.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Mahayni
Seconded by: Davis
Voting aye: Davis, Goodman, Mahayni, Larson, Orazem, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 27'day of April, 2010.