HomeMy WebLinkAbout~Master - Completion of Ames Community Development Park Subdivision, 4th Addition RESOLUTION NO. 10-028
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR AMES COMMUNITY DEVELOPMENT PARK SUBDIVISION,
4TH ADDITION (SOUTH BELL AVENUE)
FOR THE CITY OF AMES,IOWA
WHEREAS,the Public Works Department has filed a certificate of completion for the Ames
Community Development Park Subdivision,4`'Addition,for the City of Ames,Iowa,in accordance
with a contract dated March 10, 2009, by and between the City of Ames, Iowa, and Keller
Excavating, Inc., of Boone, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Ames Community Development Park Subdivision,
4`'Addition,has been fully completed by the Contractor in accordance with the terms of
the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $772,711.53.
Section 3. The amount due Keller Excavating, Inc., of Boone, Iowa, is hereby ordered
paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 26t'day of January, 2010.
`4 Vim' �lv
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Mahayni
Seconded by: Orazem
Voting aye: Davis, Goodman, Larson, Mahayni, Orazem, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 26t" day of January, 2010.