HomeMy WebLinkAbout~Master - Task Order No. 1 for New Water Treatment Plant RESOLUTION NO. 09-499
RESOLUTION APPROVING TASK ORDER NO. 1 FOR
NEW WATER TREATMENT PLANT
FOR THE CITY OF AMES
WHEREAS, at the July 14, 2009, meeting, the City Council approved the decision to construct a new 15
million-gallon-per-day lime-softening Water Treatment Plant at a new site; and,
WHEREAS, in early 2008, staff conducted a comprehensive interview process to select a consultant to
perform the Infrastructure and Capacity Needs Assessment for the existing Water Treatment Plant; and,
WHEREAS,the consultant selection process included evaluating firms on expertise needed both in the initial
assessment phase and that which would be required when the project transitioned into a design contract; and,
WHEREAS,on August 12,2008,the Council awarded aprofessional services agreement to FOX Engineering
Associates of Ames,Iowa,to complete the Infrastructure and Capacity Needs Assessment at a cost of$243,000;and,
WHEREAS,on July 14,2009,the Council approved the recommendation to begin preparations for this new
facility, and staff asked FOX Engineering to prepare a proposed scope of work for developing the necessary plans
and specifications; and,
WHEREAS,to facilitate an agreement that can expand and contract based on the actual needs of the project,
FOX Engineering has proposed a form of contract that uses a"Master Agreement"containing all of the basic contract
provisions and individual"task orders"that can be executed over time to add or remove specific work elements;and,
WHEREAS, staff has negotiated a Master Agreement with FOX Engineering that outlines the general
contractual relationship between the City and FOX Engineering; and,
WHEREAS, staff has also negotiated the first task order with FOX,which includes only those pre-design
activities that can be completed prior to land acquisition; and,
WHEREAS, examples of work that will be completed under Task Order No. 1 include finalizing the
technology selection,preliminary sizing of equipment and treatment basins,developing a preliminary plant hydraulic
profile,developing building space needs,preparing preliminary process and instrumentation diagrams,and assisting
with the site acquisition process and evaluating the suitability of candidate sites; and,
WHEREAS,reimbursement for Task order No. 1 is proposed as an hourly fee,plus expenses capped at an
amount not to exceed$358,500 without prior approval.
NOW, THEREFORE,BE IT RESOLVED by the City Council of the City of Ames,Iowa,that Task Order
No. 1 to the Master Agreement with FOX Engineering in an amount not to exceed$358,500 without prior approval
is hereby approved.
ADOPTED THIS 13t'day of October,2009.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Doll
Seconded by: Goodman
Voting aye: Doll, Goodman,Larson,Mahayni,Popken,Rice
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 13`i'day of October, 2009.