HomeMy WebLinkAbout~Master - Completion of GT1 Motor Control Center Installation Project RESOLUTION NO. 09-139
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR GAS TURBINE NO. 1 MOTOR CONTROL CENTER INSTALLATION PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Gas Turbine No. 1 Motor Control Center Installation Project for the City of Ames, Iowa, in
accordance with a contract dated March 27,2007,by and between the City of Ames,Iowa,and Baker
Electric, Inc., of Des Moines, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Gas Turbine No. 1 Motor Control Center Installation
Project has been fully completed by the Contractor in accordance with the terms of the
contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $30,557.99.
Section 3. The amount due Baker Electric,Inc.,of Des Moines,Iowa, is hereby ordered
paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 14th day of April, 2009.
C�A�?. UY-d& A. V1'
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Goodman
Seconded by: Popken
Voting aye: Doll, Goodman, Larson, Popken, Rice
Voting nay: None Absent: Mahayni
Resolution declared adopted and signed by the Mayor this 14' day of April, 2009.