HomeMy WebLinkAbout~Master - Change order for 161-kV Substation Construction RESOLUTION NO. 07-252
RESOLUTION APPROVING CHANGE ORDER NO. 3
ON CONTRACT WITH
Z CONTRACTING,INC.,
D/B/A NATIONAL CONDUCTOR CONSTRUCTORS
FOR 161-KV SUBSTATION CONSTRUCTION
FOR THE CITY OF AMES,IOWA
WHEREAS, it has been determined that a Change Order is necessary and proper on the
above contract.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that Change Order No.3 on contract with Z Contracting,Inc.,d/b/a National Conductor Constructors
of Brainerd, Minnesota, for the 161-kV Substation Construction Project be approved and adopted
as attached hereto and made a part hereof by this reference.
ADOPTED THIS 7`' day of June, 2007.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Mahayni
Seconded by: Doll
Voting aye: Doll, Goodman, Larson, Mahayni, Popken
Voting nay: None Absent: Rice
Resolution declared adopted and signed by the Mayor this 7"day of June, 2007.