HomeMy WebLinkAbout~Master - Completion of Stange Road Substation Project RESOLUTION NO. 06-324
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR STANGE ROAD 161/69-KV SUBSTATION CONSTRUCTION
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Stange Road 161/69-kV Substation Construction for the City of Ames, Iowa, in accordance with a
contract dated September 27, 2005, by and between the City of Ames, Iowa, and L.E. Myers
Company of Marshalltown, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Stange Road 161/69-kV Substation Construction has
been fully completed by the Contractor in accordance with the terms of the contract and
is hereby accepted and approved.
Section 2. The total cost of the contract is $931,186.41.
Section 3. The amount due L.E. Myers Company of Marshalltown, Iowa, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8t'day of August, 2006.
Aj
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Popken
Seconded by: Hamilton
Voting aye: Doll, Goodman, Hamilton, Mahayni, Popken, Rice
Voting nay: None Absent: None