HomeMy WebLinkAbout~Master - Close-out of contract for CyRide Bus Storage Addition RESOLUTION NO.06-182
RESOLUTION APPROVING CLOSE-OUT OF EXISTING CONSTRUCTION CONTRACT WITH
WELKER CONSTRUCTION FOR CYRIDE BUS STORAGE ADDITION AND ISSUING
SUPPLEMENTAL CONTRACT FOR REMAINING WORK
FOR THE CITY OF AMES,IOWA
WHEREAS,Welker Construction was awarded a$1.2 million contract on February 22,2005,to expand
bus storage by 9,000 square feet on the south side of the building; and,
WHEREAS,contract terms read,"payment will be made of 95%of the value of satisfactory construction
completed during the preceding calendar month...."; and,
WHEREAS,work on the addition was determined to be substantially complete on December 1, 2005,
and since reaching substantial completion,work has progressed on remaining punch list items to the point where
there is an estimated$30,822 remaining on the contract; and,
WHEREAS,this includes a change order in process in the amount of$20,100 and remaining punch list
work that includes$10,722 for landscaping, exterior finish work, and painting; and,
WHEREAS,Welker Construction is requesting that the Ames Transit Agency pay for all work completed
and stored to date, including the bulk of project retainage; and,
WHEREAS,to reflect this,Welker has submitted an invoice for$79,322.50,and authorizing a contract
close-out will allow the invoice to be paid as presented and project retainage to drop from$65,002.35 to$30,822;
and,
WHEREAS,a detailed review conducted with the assistance ofthe City Attorney and Purchasing Division
shows two options available with respect to contract close-out and retainage: 1)close-out the existing contract and
issue a supplemental contract for the work remaining ($10,722) under the same terms and conditions as the
original contract; or,2)issue a change order to reduce the amount of retainage as permitted by Iowa law; and,
WHEREAS, Welker Construction has submitted necessary paperwork to allow contract close-out
(Option 1).
NOW,THEREFORE,BE IT RESOLVED by the City Council of the City of Ames,Iowa,that the close-
out of the existing construction contract with Welker Construction for the CyRide Bus Storage Addition is hereby
approved,and a supplemental contract for the remaining work($10,722)under the same terms and conditions as
the original contract will be issued.
ADOPTED THIS 9'day of May, 2006.
• `�l�Yv Vim' �I��
.Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Goodhue
Seconded by: Goodman
Voting aye: Doll, Goodhue, Goodman,Mahayni,Popken, Rice
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 9th day of May,2006.