HomeMy WebLinkAbout~Master - Agreement for East Lincoln Way Widening RESOLUTION NO.04-149
RESOLUTION APPROVING SUPPLEMENTAL AGREEMENT WITH
SNYDER&ASSOCIATES FOR ENGINEERING SERVICES FOR
EAST LINCOLN WAY WIDENING
FOR THE CITY OF AMES
WHEREAS,the 2004/09 Capital Improvement Program(CIP)provides$4,000,000 of G.O.Bond financing
for a project in 2004/05 to reconstruct East Lincoln Way from the Skunk River Bridge to Interstate 35; and,
WHEREAS,prior to design of the project,the Council contracted with Snyder&Associates for preliminary
design services to work with the area property owners and determine a design concept that would meet their needs
and the needs of the traveling public;and,
WHEREAS,the preliminary design study looked at traffic projections,traffic accidents,pavement condition,
and turning lane needs; and,
WHEREAS, the existing pavement is in poor to very poor condition and can not be economically
rehabilitated,and there is a need to provide for left turn lanes at the intersections and many of the driveways to major
businesses; and,
WHEREAS,the design considerations included phasing of the project to minimize interruption to driveway
access,available right-of-way,pedestrian and bicycle safety, and utility conflicts; and,
WHEREAS,the analysis of the traffic volumes and turn lanes indicated the need for a five-lane facility from
the Skunk River Bridge to Dayton Avenue,a three-lane street from Dayton Avenue to 1-35,and a bike/pedestrian trail
from east of Cherry Avenue to the interstate;and,
WHEREAS,the preliminary design study was accepted by the Council in October 2003;and,
WHEREAS,it is now time to initiate the final design and preparation of the plans and specifications for this
project, and because the City contracted with Snyder & Associates for the initial study and it has developed an
extensive knowledge of the corridor area,it is appropriate to continue with this firm as the design is completed;and,
WHEREAS,the cost for Snyder&Associates'services total$355,695.
NOW,THEREFORE,BE IT RESOLVED by the City Council of the City of Ames,Iowa, that Supplement
Agreement No. 1 for engineering services with Snyder&Associates for the East Lincoln Way Widening Project is
hereby approved.
ADOPTED THIS 13"'day of April,2004.
Diane R. Voss,City Clerk Ted Tedesco,Mayor
Introduced by: Goodhue
Seconded by: Vegge
Voting aye: Cross,Goodhue,Goodman,Mahayni,Vegge,Wirth
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 13t'day of April, 2004.