HomeMy WebLinkAbout~Master - Completion of 2002/03 Concrete Pavement Reconstruction Program RESOLUTION NO. 03-464
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR 2002/03 CONCRETE PAVEMENT RECONSTRUCTION PROGRAM-
CONTRACTS 1 AND 2 (EAST THIRD STREET AND EAST AVENUE AND
GREENSBORO DRIVE, TORREY PINES ROAD,AND TORREY PINES CIRCLE)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2002/03 Concrete Pavement Reconstruction Program - Contract 1 (East Third Street and East
Avenue)and Contract 2(Greensboro Drive,Torrey Pines Road,and Torrey Pines Circle)for the City
of Ames,Iowa,in accordance with a contract dated September 24,2002(Contract 1),and March 25,
2003 (Contract 2)by and between the City of Ames, Iowa, and Manatt's, Inc., of Brooklyn, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contracts for the 2002/03 Concrete Pavement Reconstruction
Program - Contract 1 (East Third Street and East Avenue) and Contract 2 (Greensboro
Drive, Torrey Pines Road, and Torrey Pines Circle) have been fully completed by the
Contractor in accordance with the terms of the contract and is hereby accepted and
approved.
Section 2. The total cost of the contract for Contract 1 is $76,965.61; and,the total cost
of the contract for Contract 2 is $236,017.05.
Section 3. The amounts due Manatt's, Inc., of Brooklyn,Iowa, are hereby ordered paid
as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 16`h day of December, 2003.
Diane R. Voss, City Clerk Ted Tedesco, Mayor
Introduced by: Cross
Seconded by: Hoffman
Voting aye: Cross, Goodhue, Hoffman, Mahayni, Wirth
Voting nay: None Absent: Vegge
Resolution declared adopted and signed by the Mayor this 16' day of December, 2003.