HomeMy WebLinkAbout~Master - Payment for Unit No. 8 maintenance at Power Plant RESOLUTION NO. 03-242
RESOLUTION APPROVING PAYMENT TO
W-S INDUSTRIAL SERVICE,INC., FOR
UNIT NO. 8 MAINTENANCE AT THE POWER PLANT
FOR THE CITY OF AMES
WHEREAS, Unit No. 8 was taken off line in April for planned maintenance work; and,
WHEREAS, during the outage,W-S Industrial Service,Inc.,was issued a purchase order in
the amount of$35,800 to water wash the furnace walls for tube thickness mapping; and,
WHEREAS, after starting the work, it was noted that there were large amounts of slag
hanging overhead in the furnace area which is a potential falling hazard for the workers below;and,
WHEREAS, work was halted while the slag was removed; and,
WHEREAS,W-S Industrial Service,Inc.,had standby costs for personnel and equipment in
the amount of$19,008; and,
WHEREAS,the original amount for the planned maintenance work was$35,800 which now
brings the total amount due W-S Industrial Service, Inc., to $54,808.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the payment of$54,808 to W-S Industrial Service, Inc., is hereby approved.
ADOPTED THIS 24t' day of June, 2003.
C�A�?. Ly-d& �4
Diane R. Voss, City Clerk Ted Tedesco, Mayor
Introduced by: Mahayni
Seconded by: Wirth
Voting aye: Cross, Goodhue, Mahayni, Vegge, Wirth
Voting nay: None Absent: Hoffman
Resolution declared adopted and signed by the Mayor this 24t'of June, 2003.