HomeMy WebLinkAbout~Master - Engineering services contract for East Lincoln Way Widening Project RESOLUTION NO. 02-274
RESOLUTION APPROVING ENGINEERING SERVICES CONTRACT
WITH SNYDER&ASSOCIATES FOR
EAST LINCOLN WAY WIDENING PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the East Lincoln Way Widening project was programmed in the 2001-06 City's Capital
Improvement Plan for developing the project design concept and preparing preliminary design plans in 2001/02,
and funding for this preliminary project work is included in the adopted 2001/02 budget; and,
WHEREAS,due to fmding constraints and priority changes,the East Lincoln Way Widening project is now
programmed in the 2002/07 CIP,for final design to occur in 2004 and construction of the project to occur in 2005;
and,
WHEREAS,although the actual construction was delayed,it is appropriate to continue with the preliminary
design concept and preliminary design in order to determine more definitive costs; and,
WHEREAS, in addition, right-of-way needs will be determined and the associated costs included in the
future project budget;
WHEREAS, through a formal process, City staff has selected the firm of Snyder&Associates, Inc., of
Ankeny, Iowa, to develop the project design concept and prepare the preliminary and final design plans of the
project; and,
WHEREAS, Snyder& Associates has provided an Engineering Services Agreement for developing the
project design concept and preparing the preliminary design plans for a fee of$99,750.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa, that the
Engineering Services Agreement with Snyder&Associates, Inc., of Ankeny, Iowa, in the amount of$99,750 is
hereby approved.
ADOPTED THIS 14th day of May, 2002.
Diane R. Voss,City Clerk Ted Tedesco, MaN or
Introduced by: Goodhue
Seconded by: Hoffman
Voting aye: Cross, Goodhue,Hoffinan,Quirmbach,Vegge,Wirth
Voting nay: None Absent:
Resolution declared adopted and signed by the Mayor this 14t'day of May, 2002.