RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR WASTEWATER FLOW METER PROJECT
FOR THE CITY OF AMES, IOWA
WHEREAS,the Water and Pollution Control Department has filed a certificate of completion
for the Wastewater Flow Meter Project for the City of Ames, Iowa, in accordance with a contract
dated September 26, 2000, by and between the City of Ames, Iowa, and Ames Trenching and
Excavating, Inc., of Ames, Iowa; and,
WHEREAS, Iowa State University(ISU) is participating in the expense of this project on a
50150 cost-share basis; and,
WHEREAS,the contractor has already been paid 95%of the contracted amount in accordance
with contract documents, and the City has withheld $3,464.20 as retainage.
NOW,THEREFORE,BE IT HEREBY RESOLVED bythe City Council ofthe City ofAmes,
Iowa, as follows:
Section 1. The total contract for the Wastewater Flow Meter Project has been fully
completed by the Contractor in accordance with the terms of the contract and is hereby
accepted and approved.
Section 2. The total cost of the contract is $69,284.00.
Section 3. The retaining payment of$3,464.20 due Ames Trenching and Excavating,Inc.,
of Ames, Iowa, is hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8'day of January, 2002.
Diane R. Voss, City Clerk Ted Tedesco, Mayor
Introduced by: Goodhue
Seconded by: Quirmbach
Voting aye: Goodhue, Hoffinan, Quirmbach, Vegge, Wirth
Voting nay: None Absent: Cross
Resolution declared adopted and signed by the Mayor this 8' day of January, 2002.