HomeMy WebLinkAbout~Master - Completion of 2000/01 Storm Sewer Intake Rehabilitation Program RESOLUTION NO. 01-393
RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR 2000/01 STORM SEWER INTAKE
REHABILITATION PROGRAM
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2000/01 Storm Sewer Intake Rehabilitation Program for the City of Ames,Iowa,in accordance with
a contract dated April 11,2000,by and between the City of Ames,Iowa,and Armstrong Company,
Inc., of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2000/01 Storm Sewer Intake Rehabilitation Program
has been fully completed by the Contractor in accordance with the terms of the contract
and is hereby accepted and approved.
Section 2. The total cost of the contract is $107,440.01.
Section 3. The amount due Armstrong Company,Inc.,of Ames,Iowa,is hereby ordered
paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 28th day of August, 2001.
Diane R.Voss,City Clerk Ted Tedesco,Mayor
Introduced by: Hoffman
Seconded by: Quirmbach
Voting aye: Cross, Hoffman, Quirmbach, Wirth
Voting nay: None Absent: Campbell, Goodhue
Resolution declared adopted and signed by the Mayor this 28th day of August, 2001.