HomeMy WebLinkAbout~Master - Change Order for U.S. Hwy. 30/South Dakota Grading & Paving Project RESOLUTION NO. 01-321
RESOLUTION APPROVING CHANGE ORDERS FOR THE
U. S. #30 AND SOUTH DAKOTA AVENUE INTERCHANGE
GRADING AND PAVING PROJECT
FOR THE CITY OF AMES, IOWA
WHEREAS, over the past several years, staff has been working to complete the layout and
design of an interchange to be constructed at the intersection of South Dakota Avenue and U. S. #30;
and,
WHEREAS, the interchange project includes grading, paving, bridge construction, drainage,
signage, lighting, and acquisition of right-of-way and access control; and,
WHEREAS,when grading started,areas of wet soils were encountered that required extra work
to be completed,and Change Order No. 1 was issued and approved by staff in the amount of$1,500 for
the installation of additional safety fencing along the Newbury apartment site; and,
WHEREAS, Change Order No. 2 involves work in the amount of$24,290.50 to authorize
additional tiling in the interchange; and,
WHEREAS, Change Order No. 3 in the amount of$19,627.20 is to authorize the extension of
the outlet tile from the interchange area; and,
WHEREAS, another item of extra work consisted of excavating wet soil and placing dry soils
in the areas excavated, and Change Order No. 4 will amount of$39,369.22; and,
WHEREAS,approximately$670,000 is available forproject contingencies,and the$84,786.92
in change orders would be paid from these contingency funds.
NOW,THEREFORE,BE IT RESOLVED by the City Council of the City of Ames,Iowa, that
Change Orders No. 1 thru 4 totaling$84,786.92 for the U. S.#30 and South Dakota Interchange project.
ADOPTED THIS 24th day of July, 2001.
LXJdl- toe
Diane R.Voss,City Clerk Ted Tedesco,Mayor
Introduced by: Goodhue
Seconded by: Hoffman
Voting aye: Campbell, Goodhue, Hoffinan, Quirmbach, Wirth
Voting nay: None Absent: Cross
Resolution declared adopted and signed by the Mayor this 24th day of July, 2001.