HomeMy WebLinkAbout~Master - Completion of Billy Sunday Road Paving Project RESOLUTION NO. 00-552
RESOLUTION ACCEPTING AS COMPLETE AND
SATISFACTORY WORK DONE UNDER CONTRACT FOR THE
BILLY SUNDAY ROAD PAVING PROJECT;ORDERING FINAL
PAYMENT,DETERMINING AMOUNT TO BE ASSESSED;AND
ORDERING FINAL PLAT AND SCHEDULE
WHEREAS, the City's Engineers have reported that they have inspected the work and find it in
compliance with the terms of the contract for the Billy Sunday Road Paving Project; and,
WHEREAS, the City Council is now asked to accept said work and authorize payment;
NOW, THEREFORE, BE IT RESOLVED,by the City Council for the City of Ames, Iowa:
Section One. The work done pursuant to the contract for the Billy Sunday Road Paving Project is
hereby accepted as complete and satisfactory.
Section Two. If, after the thirtieth day from the date of this acceptance no valid claims have been
or remain filed against the amounts retained and unpaid under the contract,and all other performance
required of the contractor is found to be completed,the Director of Public Works shall cause the said
retained amount to be paid to the contractor, as well as any other amount due the contractor.
Section Three. The total cost of the said project is$205,806.13,not more than$205,806.13 of which
shall be assessed to the benefitted property owners.
Section Four. Within thirty days hereof the engineers shall file with the City Clerk a final
assessment schedule showing:
a. a description of each lot to be assessed;
b. the valuation of each lot as fixed by the Council;
C. the amount to be assessed against each lot,which shall include the assessment for the default
fund, and the amount of deficiency, which may be subsequently assessed against that lot
under Section 384.63, Code of Iowa.
Adopted this 19th day of December , 2000.
By�>CI�QN11Z�� LJ��1 By
Diane R. Voss, City Clerk Ted Tedesco, Mayor
Billy Sunday Road Paving-121900