WHEREAS,the Public Works Department has filed a certificate of completion for the 1998-
99 Ames Municipal Airport Improvements(Terminal Apron Improvements)for the City of Ames,
Iowa,in accordance with a contract dated July 13, 1999,by and between the City of Ames,Iowa,and
Manatt's, Inc., of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 1998-99 Ames Municipal Airport Improvements
(Terminal Apron Improvements) has been fully completed by the Contractor in
accordance with the terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $470,904.69.
Section 3. The amount due Manatt's, Inc., of Ames, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8th day of February, 2000.
Diane R. Voss, City Clerk Ted Tedesco, Mayor
Introduced by: Campbell
Seconded by: Wirth
Voting aye: Campbell, Goodhue, Hoffman, Quirmbach, Wirth
Voting nay: None Absent: Cross
Resolution declared adopted and signed by the Mayor this 8th day of February, 2000.