HomeMy WebLinkAbout~Master - Additional Engineering Services Payment for 5th Street Project RESOLUTION NO. 99-457
RESOLUTION APPROVING REQUEST FROM
ENGINEERING PLUS FOR ADDITIONAL
CONSTRUCTION OBSERVATION AND DESIGN SERVICES
FOR THE 5TH STREET STREETSCAPE IMPROVEMENT PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, City Council approved an agreement for construction observation services for the 5th Street
Streetscape project with Engineering Plus on July 28, 1998; and,
WHEREAS,the professional services contract with Engineering Plus provided for changes,however,the changes
had to be requested in writing prior to them taking place; and,
WHEREAS, in this case, the request for additional expenses came after the work was completed, and thus by
contract,the staff could not authorize the increased payment;and,
WHEREAS,the increased cost was due to the construction inspection services portion of the contract since the
construction activities extended longer than programmed; and,
WHEREAS,the contract with Engineering Plus does not directly address how they would be compensated if the
project completion date was extended beyond September 15, 1998; and,
WHEREAS,after further review with the consultant and the contractor,staff agreed that the contract completion
date should be adjusted to October 7,1998,to compensate for the additional quantities of work that were completed as part
of the project; and,
WHEREAS,the construction project completion date was extended by 22 calendar days to October 7, 1998,and
the amount ofthe time extension was determined from the percentage the final contract amount increased over the original
contract amount,which was 17.89%;and,
WHEREAS,staff feels that the construction observation services agreement should also be extended to October
7, 1998,and the consultant fee increased by the same percentage; and,
WHEREAS,using this rational,the increase in the fee based on 17.89%additional time is$6,081; and,
WHEREAS, Engineering Plus also requested $778 for designing a structural wall to enclose a vault under the
sidewalk at the Octagon building,and staff feels that those costs are fair and should be reimbursed.
NOW,THEREFORE,BE IT RESOLVED by the City Council of the City of Ames,Iowa, that payment in the total
amount of$6,859 to Engineering Plus for additional construction observation and design services for the 5th Street
Streetscape Improvement Project is hereby approved.
ADOPTED THIS 14th day of December, 1999.
C:�51�?- 0-d&- '�4
Diane R. Voss, City Clerk Ted Tedesco, Mayor
Introduced by: Quirmbach
Seconded by: Wirth
Voting aye: Campbell,Cross,Hoffinan,Parks,Quirmbach,Wirth
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 14th day of December, 1999.