HomeMy WebLinkAbout~Master - Accepting Completion of the Contract for the Alley Paving from 10 Street to 11th Street between Grand And Wilson RESOLUTION NO. 99-210
RESOLUTION ACCEPTING AS COMPLETE AND
SATISFACTORY WORK DONE UNDER CONTRACT FOR THE
ALLEY PAVING FROM LOTH ST TO 11TH ST BETWEEN
GRAND AND WILSON; ORDERING FINAL PAYMENT,
DETERMINING AMOUNT TO BE ASSESSED;AND ORDERING
FINAL PLAT AND SCHEDULE
WHEREAS, the City's Engineers have reported that they have inspected the work and find it in
compliance with the terms of the contract for the Alley Paving from IOth St to 11th St Between
Grand and Wilson; and,
WHEREAS, the City Council is now asked to accept said work and authorize payment;
NOW, THEREFORE, BE IT RESOLVED,by the City Council for the City of Ames, Iowa:
Section One. The work done pursuant to the contract for the Alley Paving from 1Oth St to 11th St
Between Grand and Wilson is hereby accepted as complete and satisfactory.
Section Two. If, after the thirtieth day from the date of this acceptance no valid claims have been
or remain filed against the amounts retained and unpaid under the contract,and all other performance
required of the contractor is found to be completed,the Director of Public Works shall cause the said
retained amount to be paid to the contractor, as well as any other amount due the contractor.
Section Three. The total cost of the said project is $27,523.60,not more than $13,761.80 of which
shall be assessed to the benefited property owners.
Section Four. Within thirty days hereof the engineers shall file with the City Clerk a final
assessment schedule showing:
a. a description of each lot to be assessed;
b. the valuation of each lot as fixed by the Council;
C. the amount to be assessed against each lot,which shall include the assessment for the default
fund, and the amount of deficiency, which may be subsequently assessed against that lot
under Section 384.63, Code of Iowa.
Adopted this 8th day of June, 1999.
B �GQ-!�� By