RESOLUTION ACCEPTING COMPLETION OF CONTRACT
FOR COOLING WATER SUPPLY MODIFICATION PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Department has filed a certificate of completion for the Cooling
Water Supply Modifications Project for the City of Ames,Iowa,in accordance with a contract dated
September 8, 1998, by and between the City of Ames, Iowa, and ACI Mechanical, LC, of Ames,
Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Cooling Water Supply Modification Project has
been fully completed by the Contractor in accordance with the terms of the contract and
is hereby accepted and approved.
Section 2. The total cost of the contract is $225,008.06.
Section 3. The amount due ACI Mechanical,LC,is hereby ordered paid as provided by
law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8th day of June, 1999.
Diane R. Voss, City Clerk Ted Tedesco, Mayor
Introduced by: Campbell
Seconded by: Cross
Voting aye: Campbell, Cross, Hoffman, Quirmbach, Wirth
Voting nay: None Absent: Parks
Resolution declared adopted and signed by the Mayor this 8th day of June, 1999.