Hi Jim -
Following the passage of a bond issue, it would take approximately 5 to 6 months for the design
documents to be prepared. Therefore, if a bond vote were held in July, bids would be let in January and
awarded in the spring of 2008. Construction would occur that same summer and the pool would open in
2009. If the vote were held in November, bids would be let in May and awarded mid-summer of 2008.
Minimal construction would occur that summer/fall. The majority of construction would happen in 2009
with the facility opening in 2010.
I hope this information helps. If you have other questions please let me know.
Best Regards,
Nancy Carroll, Director of Parks and Recreation
515-239-5357 Voice
515-239-5355 Fax
ncarroll@city.ames.ia.us
CITY OF AMES = "EXCELLENCE THROUGH PEOPLE"
"Jim Popken" <jim@JimPopken.org>
"Jim Popken"
<jim@JimPopken.org> To ncarroll@city.ames.ia.us
Sent by.
=1
jimpopken@gmail.com cc
05/02/2007 09:28 AM Subject Pool question
Nancy
What is the latest date for an bond issue referendom that does not impact the construction
schedule on a recreational pool.
Thanks
Jim
920 Clark Avenue