Loading...
HomeMy WebLinkAboutA014 - Council Actoin Form dated May 22, 2007 - Item 16d-e i ITEM # I1 J � Qi DATE May 22, 2007 COUNCIL ACTION FORM SUBJECT: APPROVAL OF PRELIMINARY EXPENSES PRIOR TO AQUATIC CENTER BOND REFERENDUM BACKGROUND: Should the City Council authorize a July 24th outdoor aquatic center bond referendum, it is timely to consider initiation of two important efforts at this time. The first is preparation and distribution of an educational brochure for Ames voters. The second is authorization of initial design work that would hopefully enable us to open the facility in 2009 rather than 2010 and to save hundreds of thousands of dollars in subsequent cost escalation. EDUCATIONAL BROCHURE — With a goal of educating the public about the upcoming bond referendum, approximately $4,500 is needed for the development and printing of a brochure. Funding for this expense is available in the Council's 2006-07 Contingency Account. SITE SURVEY AND SOIL BORINGS — During development of the feasibility study, RDG reviewed the soils at the site. Preliminary findings from soil borings taken in similar parts of Ames indicate that the soil at the 13th Street location appears to be sand and soft cohesive soils. This type of soil will compress when fill is placed on top of it. Fill material should set for approximately 90 days before construction begins. If not, settlement could occur that would damage the facilities at a later date. It should be noted that it is not unusual to build in these types of soils. Buildings at the Iowa State Center and Jack Trice Stadium were successfully built in these same conditions. Approximately 14' of fill will be required to support facility development in the southeast corner of the site. There are two options for how the City could proceed with the needed earthwork. It is important to note that with Option 1, it is anticipated that the facility could open in June of 2009, and with Option 2 it would probably open in June of 2010. In Option 1, the site survey and soil borings would be accomplished in June and July of 2007. This would cost $15,000 and could be completed prior to the bond referendum being held. Should the bond referendum pass, previous completion of these preliminary steps would then allow preparation of the earthwork plans and specifications immediately after the vote. This should allow the earthwork to be accomplished during late autumn and the needed settling to occur over the winter months. 1 i Development of plans and specifications for the balance of the project would not begin until the outcome of the referendum is determined on July 24t". The largest portion of the project would be bid in February 2008. Since the earthwork would already have been completed, facility construction could then begin in May 2008 with the facility opening anticipated for June 2009. In Option 2, no design work would begin until the outcome of the referendum is known on July 24th. If the referendum passes, this scenario calls for the site survey and soil borings to be done in August and September 2007. With winter weather then approaching, this timeframe would not allow for the needed window of time to accomplish the earthwork prior to the ground freezing (i.e., preparation of the bid document in October, taking bids in November, awarding the bid in December, completing the earthwork in January/February). Under Option 2, the site survey and soil boring information would be incorporated into the overall Plans and Specifications being developed between October 2007 and January 2008. The entire project, including the necessary earthwork, would be bid in February 2008 with construction beginning in May 2008. However, construction in Option 2 would be limited to the earthwork being addressed in May and June of 2008. Settling of the fill would be required during the months of July, August, and September. Then, with winter weather approaching, the majority of the facility would be built during the 2009 construction season with the facility opening to the public in 2010. If Option 2 is selected, it is also anticipated that project costs would increase by approximately $500,000. Though the bids would still be let in a timely manner in February 2008, contractors bidding the project will realize that construction during the summer of 2008 will be limited to the earthwork and settling of this fill. They will need to forecast increased costs for the bulk of construction activities to occur during 2009. ALTERNATIVES: 1. Authorize $4,500 for an educational brochure and $15,000 for completion of a site survey and soil borings. In the event the bond referendum passes, this alternative better assures that the facility can open in June 2009 with an estimated cost savings of$500,000. 2. Authorize the allocation of $4,500 for an educational brochure, but do not authorize the site survey and soil borings prior to the bond referendum. This alternative would delay the facility opening until June 2010 and bring increased costs of approximately $500,000. Facility features would likely need to be reduced in order to maintain the project budget of $8,488,000. 2 MANAGER'S RECOMMENDED ACTION: The recommendation for expending funds for the brochure is consistent with educational efforts undertaken for many previous bond referendums. This will allow our citizens to have factual information from the City upon which to base their votes. The recommendation regarding initial design work is very unusual, since staff would not normally recommend expenditures for a project that has not yet received public approval. However, the $15,000 cost represents a small fraction of the $500,000 in potential cost savings by taking these early steps prior to the referendum. This initial work could also have a major impact on when the facility opens to they public. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1 approving the allocation of $4,500 for an educational brochure and $15,000 for completion of a site survey and soil borings. It is also recommended that the brochure expense be allocated from the 2006-07 Contingency Account, and that the $15,000 site survey and soil boring expenses be taken from the Parks Development Fund available balance. 3