HomeMy WebLinkAboutA024 - Council Action Form dated March 25, 2008 ITEM # Z
DATE March 25, 2008
COUNCIL ACTION FORM
SUBJECT: NOTICE OF INTENT TO PROCEED WITH THE RAW WELL WATER
TRANSMISSION PIPELINE PROJECT AND OBTAIN EASEMENTS BY
EMINENT DOMAIN, IF NECESSARY
BACKGROUND:
The 2007-08 Capital Improvement Plan budget includes $50,000 for purchase of right-
of-way easements for the raw well water transmission pipeline. In the summer of 2007,
Water and Pollution Control Department staff began the preliminary planning. There
are four main objectives for this public improvement project with a total estimated cost
of $4,000,000.
1. Significantly increase the productivity of the city's existing well field by
approximately one million gallons a day by reducing existing pipe friction losses
2. Extend the well piping system closer to future well fields
3. Provide increased reliability and redundancy for approximately 65 percent of the
current supply capacity
4. Balance the responsibility to provide for the needs of our water utility customers
and minimize the impact to affected property owners
In October 2007, FOX Engineering Associates, Inc. was retained as the engineering
consultant to assist with detailed planning and design. Staff have worked with FOX
Engineering to identify the most cost-effective and feasible route for the 30-inch
pipeline. The selected route will require permanent easements from six different
property owners.
Staff invited all potentially affected property owners to an open house on November 27,
2007. The primary purpose of the open house was to assist property owners in
understanding the need for the project. It also allowed those potentially affected to ask
questions and give feedback to staff. In addition, either staff or FOX Engineering has
met individually with each of the property owners where permanent easements are
needed. Staff have also contacted residents in areas where permanent easements will
not be required but where construction-related disruptions will occur.
Provisions in Section 6B.2A of the Iowa Administrative Code require written notification
to each potentially affected property owner at least 30 days prior to the time the City
Council adopts a measure to declare its "intent to proceed with a public improvement
and acquisition, by condemnation if necessary, of the property." This notice was
approved at the February 12, 2008 Council meeting. That meeting also set March 25
as the date of the public hearing.
Although staff are hopeful the easements required can be negotiated without
condemnation, it is conceivable that an agreement for a voluntary sale may not be
reached; and condemnation might become necessary sometime in the future.
Therefore, the City is required by law to notify all potential property owners before
actually moving ahead with any part of this project. The attached form meets the
requirement set forth by Iowa law and was mailed to affected property owners on
February 13, 2008. In addition to the legal notice, staff have made efforts to keep
affected citizens informed by mail and by postings to the department's website project
updates to assist them in understanding the various phases of the pipeline project.
Because of the requirements imposed by state law, no offers to purchase easements
have been made.
At this time, staff is requesting the City Council to declare the city's intent to
proceed with the raw well water transmission pipeline project and authorize staff
to purchase the necessary easements for the project, using condemnation if
necessary. Staff will then initiate appraisals on the parcels identified for
purchase of easements for the raw well water transmission pipeline.
Each property owner, by right, will have the opportunity to meet with the appraiser
before the appraisal has been finalized and be provided a copy of the appraisal when
offers to purchase easements are made. Once offers have been made, a waiting period
of 10 days commences before the City or its representative can begin negotiations with
the property owners for purchase of the easements. The City is required by state law to
make good-faith efforts to reach an agreeable purchase price before the process of
eminent domain can begin. Again, staff is hopeful that voluntary agreements can be
reached, but it is conceivable that condemnation might be necessary to complete the
project.
Staff has received suggested route modifications from four of the property owners who
will be impacted by permanent easements through their property.
For Story Construction, a route adjustment was suggested and agreed to that resulted
in a $40,000 cost savings to the project. This allowed more of the pipeline to be placed
in the floodway and decreases the need to move additional materials stored by Story
Construction. This minor adjustment is reflected in the preferred route.
Representatives of the Lange parcel proposed the pipeline to be located on the east
edge of the property. Due to increased construction prices of clearing and grubbing of
multiple large oak trees and burying the pipe deeper to avoid existing old river channel
ox bows, as well as additional length of pipe and extra fittings, the consulting engineer
estimates the cost of this suggestion to be $250,000 more than the estimate of the
preferred route. This route modification is not reflected in the preferred route.
Y
Regarding the Pyle property, the owner would like to either move the pipeline west of
the river or put the pipeline on the very west edge of his property. Due to future costs
associated with an additional stream crossing to extend closer to the future city well
fields, staff estimates the additional cost of the first suggestion to move the pipeline to
the west side of the river to be $209,000. Given additional construction costs
associated with extra fittings for extra bends in the pipeline and additional length of
pipeline, staff estimates the cost of his second suggestion to be $90,000 more than the
preferred route. These route modifications are not reflected in the preferred route.
Regarding the Hickory Park parcel, the owner would like to move the pipeline as close
to the west edge of the property as possible. The estimated cost of this modification is
$24,000 more than the preferred route due to additional pipe length and fittings. Moving
the pipeline closer to the South Skunk River could mean stream bank stabilization may
be required. This requirement and the costs associated have not been determined at
this time. These route modifications are not reflected in the preferred route.
ALTERNATIVES:
1. Approve a resolution to proceed with the raw well water transmission pipeline public
improvement project and authorize staff to acquire the necessary easements for the
selected route, using eminent domain if necessary.
2. Direct staff to modify the selected route on the identified affected properties and
approve a resolution to proceed with the raw well water transmission pipeline project
with modifications and authorize staff to acquire the necessary easements for the
project, using eminent domain if necessary.
3. Direct staff to redesign the project to alter the number and location of impacted
properties, requiring the public notification process to start over, if necessary by law.
4. Do not initiate any activity on this project at this time.
MANAGER'S RECOMMENDED ACTION:
The raw well water transmission pipeline project is an important component of the water
utility's source water development plan. The pipeline will serve all customers of the
water utility by providing increased reliability and redundancy for the raw water delivery
system and will actually increase the available raw water capacity. Staff is working
closely with the consultant to prepare a route that balances the important goals of
minimizing the cost to all customers, while minimizing the impacts to individual property
owners. Therefore, it is the recommendation of the City Manager that the City Council
adopt Alternative No. 1 and approve proceeding with the raw well water transmission
pipeline public improvement project and authorizing staff to acquire the necessary
easements for the project, using condemnation if necessary.
Based on our conversations, it appears that three of the six property owners who will be
impacted by permanent easements are suggesting modifications to the consultant's
preferred route. If the City Council wishes to direct staff to modify the preferred
route within the identified affected property owners in response to any of the
property owners' suggestions, the Council should adopt Alternative No. 2 and
identify the changes to be made. If the City Council wishes to direct staff to redesign
the project altering the number and location of impacted properties, the Council should
adopt Alternative No. 3 and refer the matter back to staff to notify the public of the
change in the route.
NOTICE OF A PUBLIC HEARING TO CONSIDER A PROPOSED PUBLIC
IMPROVEMENT PROJECT TO
CONSTRUCT A RAW WELL WATER TRANSMISSION PIPELINE
To owner(s) and any contract purchaser(s):
Name
Address
Name
Address
Under the provisions of Section 613.2A of the Code of Iowa, a governmental body which
proposes to acquire property under power of eminent domain for a public improvement project is
required to give notice of intent of a proposed public improvement project to all property owners
and contract purchasers, whose property or parts thereof, or interest therein,proposed to be
acquired for the project, which may be subject to condemnation.
1. NOTICE OF PROPOSED PUBLIC IMPROVEMENT
Notice is hereby given that the City of Ames,Iowa(the Acquiring Authority)will consider
giving final approval to fund the site-specific design, the selection of the proposed route or
site location for this public improvement, and to authorize the completion of this public
improvement. The Acquiring Authority proposes, but has not yet given final approval, to
open negotiations to acquire the property, easement(s), or other rights in real property
necessary to construct this public improvement, or to institute condemnation proceedings,
if necessary to do so.
2. DESCRIPTION OF THE GENERAL NATURE OF THE PUBLIC
IMPROVEMENT
The proposed public improvement project is as shown on a project plan prepared by:
FOX Engineering Associates Inc., Ames, Iowa; and consists of approximately 14,000 feet
of 30-inch water main for the purpose of conveying raw water from city wells to the water
treatment plant.
3. INTENDED USE OF PRIVATE PROPERTY TO BE ACQUIRED
A. The proposed route or site location of the above-described public improvement is
shown on the project plan.
B. If the Acquiring Authority undertakes to construct the above-described project, it
will be necessary to acquire land for water pipeline purposes and, as may be
necessary, to acquire permanent water main easements and temporary construction
easements by negotiated purchase; otherwise, it will be necessary for the City to
proceed to institute condemnation to acquire the property rights needed to
Page 1
construct and maintain the public improvement.
4. ACTION REQUIRED TO PROCEED WITH THE PROJECT: OPPORTUNITY
FOR PUBLIC INPUT
In order to proceed with the above-described project and complete the acquisition of
property and property rights needed for the project, the Acquiring Authority will hold a
public hearing to consider giving final approval to fund the site-specific design for the
public improvement, to make a final selection of the route or site location for the public
improvement, to proceed with the construction of the project, and to authorize acquisition
of private property rights needed for the project by condemnation proceedings, if
necessary, on the 25th day of March 2008. You may appear in person at the public
hearing and provide input into this process. You may also contact the Acquiring
Authority in writing not later than 12:00 p.m. the 25th day of March 2008.
You may contact Christina Murphy, P.E., Assistant Director, Water &Pollution Control
Department at 300 E. 5`h St., Bldg. 1, Ames, Iowa 50010, and by phone at 515-239-5150
for information regarding the public improvement.
5. TIME, DATE, AND PLACE FOR PUBLIC HEARING
The public hearing will be held at 7:00 P.m. on the 25th day of March 2008 in Council
Chambers at the city s regular council meeting.
The Project Plan and Statement of the Rights of Individual Property Owners are on file
and available for review at the Ames Water and Pollution Control Department, 300 East
5th St., Building 1, Ames, 1A 50010.
(Printed Name &Title)
, Iowa
Attachment: Statement of the Rights of Individual Property Owners
Page 2
`
. 'VIM
Well Water Transmission Main
Project Update
City Council Briefing
AT
March 25, 2008
1 FOX '`
Leslie Wolfe. P.E. Christina Murphy. P E
Protect Manager Assistant Director
Fox Engineering Water&Pollution Control
BACKGROUND
Key Components of Water Supply
1 . Adequate Source Water Supply
— Wells
5 new wells in 10 years -12 MGD drought
yield
— Conveyance Capacit
Ability to move water through pipes from
the supply wells to the treatment facility
o k, 2. Treatment Capacity
1
PROJECT OBJECTIVES
• Provide increased reliability and
redundancy for approx. 65% of the current
supply capacity
• Increase the productivity of existing well
fields by approx. 1 MGD by reducing
-- "�- existing pipe friction losses
• Extend the well piping system closer to
future well fields
• Balance between customers & affected
property owners
Airier
�bl E�
I
FUTURE WELL FIELDS
2
FUNDING
FY 07/08 $ 500,000 Engineering, Easements, Permits
FY 08/09 $1,500,000 Engineering, Construction
131
FY 09/10 $2,000,000 Construction
Total Estimated
Project Cost $4,000,000
t1l�ER._ �
\
PUBLIC INPUT
• Nov 27, 2007 Project Open House
(letter mailed and follow-up phone call)
• Permission granted for preliminary work (i.e.
geotechnical, environmental, survey)
�• Information packets mailed if requested.
• One-on-one meetings offered
Met with all property owners of permanent
� easements required for the project
• Sent informational letters and notice of public
hearing to all affected property owners (Feb 13tn)
• Created project construction webpage on
-'` department website for updates during design and
construction
3
CORRIDOR
AREA I"
Lincoln Way
RAW WATER
MAIN CORRIDOR
_ 1
t iW-1 30
�t�• YOUTH SPORTS
COMPLEX
Alternate
Route
Study Des a r
Lincoln Way
10 Routes Studied y
floodway� d
-SOUTH
C
-MIDDLE x
-NORTH c
Squaw d d
S
Creek 3
creened
3 Y
R C
• Dayton Ave. ¢ n
w
�101h
HWY 30 IIfy To Future Wells
IN YSC weirs
4
SCREENED ROUTES
- � • M s
CARNEGIE
Lincoln Way
SONDROL
tt'•;;Tk�
• ,SOUTH ROUTE Lincoln Way
Floodway FLOODWAY
All private easements
Shortest length
Mostly undevelopable FREEL DR
Less bends
rreel Drive
Business interruptions
- Utility conflicts S. 16th
- Street replacement
- +$500,000 HWY 30
N� YSC Wells
5
MIDDLE ROUTE
Iowa State Story
Ready Mix Construction
i
a
Lincoln W
Iowa State Ready Mix Story Construction
Longer pipe length Shorter pipe length
Additional easement Fewer bends
Rubble fill
NORTH ROUTE
a
- s
6 E 7th
E 6th -
s,
■ P
MP 71" St. E 6th St.
Utility conflicts Eastwood apts Access maintained
Higher design& -access Existing easement
N� t construction costs -location
6
RESULTS
Section Environmental People Construction Cost
South
1. Floodway $
2. Freel Dr. _ ® $$
Middle
1. ISRM _ $$
2. Story Const. $
North
1. 6lh St. _ _- $$
2. 7th St. a $$
J -
3.Water Plant $$$
�n ut
1lA
SELECTED
ROUTE
Lincoln Way
13,200-Ft of 30"pipe
8 5% Floodway.
Floodway or City Property >
a •
o
Permanent Easements = 6 squaw
Creek 3
3' Y
c6 C
cr 7
Y
Properties affected w `n
S.1stn
by construction (including
6rh residents)= 31
hire HWY 30 ��
11l To Future Wells
YSC Wells
7
STORY CONSTRUCTION
Original
Alignment
Preferred ••••��•••
Route
•
•
•
Original Alignment •
5243.000
Preferred Alignment
5203.000
S40.000 Lincoln Way
tit Cost Savings
PYLE LAND LLC
n
rS. t 6th . . . . . .•
r '
West Side •
Altemate • � East River
' • • Bank
l Alternate
r •
HWY 30 • ■ to■�To Future
? � ■ ■s ■ ■ • ■ Wells
•~ rSC Wells
Preferred
Route
1Va
PYLE LAND LLC
West Side Alternate • • • • • • • • • •
($26,400)—Pyle Route vs. Selected Route
$235,400—Future Water Main Extension
$209,000 Cost Increase vs. Preferred Route
East River Bank Alternate
$90,000 Cost Increase vs. Preferred Route
' tia
I
HICKORY PARK
' Alternate
•
Alignment Preferred Alignment- $325,000
■
Alternate Alignment- $349,000
•
•
$24,000
Cost Increase
Preferred
Route
s
r Floodway
cc
Y
N O
N
S 16"St
9
LANGE
Lincoln
•
Preferred Route- $450,000 Floodway
■
Altemate Alignment-$700,000
Preferred
$250,000 Route
Cost Increase
Alternate ;
Alignment
■
■
a
•
•
Timeline
February 12,2008 30-0ay Notice of Public Hearing regarding the public improvement
project declared at meeting of Ames Ctty Council.
March 25,2008 Public hearing for Public Improvement Project.
March 28,2008' Property owners of locations where permanent easements need
to be purchased will be contacted by the appraiser hired by the City
April 23,2008- Preliminary offers,based on appraisals,will be sent to affected property
owners.
May 5,2008' After 10-day waiting period required by state law,property owners and
negotiations for easements begin
June 10.2008' Easements are obtained,council approves and authorizes
payment
Aug/Sept 2008' Preliminary plans and specifications are approved,bid letting,and contract
award
October 2008' Construction begins
October 2009' Estimated project completion
�1 'These dates are preliminary and subject to change
10
NEXT STEPS
Pass a resolution approving proceeding with the
project and acquiring easements by condemnation, if
necessary
OR
Direct staff to modify the selected route on the
identified affected properties and approve a resolution
proceeding with the project and acquiring easements
by condemnation, if necessary
:--sr
OR
Direct staff to redesign the project to alter the number
and location of impacted properties. Start the notice
of public hearing proceedings over.
I
WA
11
I
+r
d
ra C
U E 7th St
Woo
E 6th St UP RR _ >a
` 71
I. . .�
Water '~
~I Treatment
. Plant Story Construction
Routeir
-75
a „
,�jff=
40
- Sondrol
C
E Lincoln Way
IT
—Xw�"7
N.
►'
SE Well Field Floodway Route
A 6Qft�t&- U)
it
04
:ram
a Sq4
aN• a'
p
1 � o
>�
I
w
•-- - SE 16th St
r SE 16th St
1
Hwy 30
Legend
Existing Mains
Proposed Routes r
X valves YSC Well Field
Illilim 6th
111111ill Story Construction
Floodway
i
FIGURE 2: Selected Route N ° 205 410 82FFeet
Zf��eerinaeline 1inchequals800feetRaw Well Water Transmission Pi p
1601 Golden Aspen Dr,Suite 103 Water & Pollution Control Department Date 2008
Prepared by::red by:AMP
Ames, Iowa 50010 Aerial Photo:2006 ISU&MIT
(515)233-0000 Fax:(515)233-0103 Ames, Iowa Project No:3338-07A 300
> df /
t
4 Cm
E 7th St — y
-,• E 6th St UP RR `+
T Water 1,
I '1're� N nt _ __ Iowa State
A 11an � ) Ready Mix Route Story Construction
- Route
AP
Sondrol
E Lincoln Way
+M
2 ♦ -
�r C
SE Well Field Floodway Route
a sqy
L c
LOEM-
VU~ .X
LU
SE 16th St SE 16th St
05000
Hwy 30 .
I
Legend
Existing Mains Sondrol
Proposed Routes Iowa State Ready Mix
M Valves Story Construction YSC Well Field
6th Carnegie
m 7th Dayton
m WTP Freel
Floodway
FOX FIGURE 1 : Alternate Routes Iv z°° 400 800
Feet
k eFOXeerina Raw Well Water Transmission Pipeline 1 inch equals 800 feet
Water & Pollution Control Department Date 08
1601 Golden Aspen Dr,Suite 103 Preparedred by by AMP
Ames, Iowa 50010 Aerial Photo:2006 ISU&MIT
(515)233-0000 Fax:(515)233-0103 Ames, Iowa Protect No:3338-07A.300
Water and Pollution Control Department
Timeline Regarding the Raw Well Water Transmission Pipeline
February 12, 2008 30-Day Notice of Public Hearing regarding the public improvement
project declared at meeting of Ames City Council. This Notice is
required to be mailed to property owners for whom easements for
the project are required. It will also be mailed to those who will be
temporarily impacted during the construction process (i.e. 6th
Street residents).
March 25, 2008 Public hearing for Public Improvement Project. Council will
approve a resolution deeming the project necessary and allow the
project to proceed and authorize obtaining easements, using
condemnation, if necessary.
March 28, 2008* Property owners of locations where permanent easements need
to be purchased will be contacted by the appraiser hired by the
City.
April 23, 2008* Preliminary easement purchase offers, based on appraisals, will
be sent to affected property owners.
May 5, 2008* After a 10-day waiting period, as stated in the Iowa Administrative
Code, city staff and/or their representative will contact property
owners to begin processing the easement documents and conduct
any additional negotiations.
June 10, 2008* Easements are obtained and filed, council approves and
authorizes payment
Aug/Sept 2008* Preliminary plans and specifications are approved, bid letting, and
contract award
October 2008* Construction begins
October 2009* Estimated project completion
* These dates are preliminary and subject to change.
Updated 3-20-08