HomeMy WebLinkAboutA004 - Memo to Mayor and Council and Parks and Recreation Commission dated August 9, 2001 i
Memo
A
City Manager's Office
TO: Mayor and City Council Members
Parks and Recreation Commission Members
FROM: Steven L. Schainker, City Manager
DATE: August 9, 2001
SUBJECT: Vision Iowa Grant Update
On Wednesday, staff from the City and Iowa State University appeared in Des Moines before the Vision
Iowa Board to present our "Connect Iowa" proposal for a$22 million grant request. Board members
had a number of questions/concerns that are summarized below:
• There was a question about the lack of documented support by the officials from the Des
Moines Botanical Center and Iowa Arboretum for the Reiman Gardens component.
• There was a concern expressed that the County Board of Supervisors had not contributed
enough to the project. This concern is due to an apparent disagreement as to whether or not
the Story County Conservation Board's commitment of "in-kind" support is the type of
direct contribution they expect from a County.
• There was a question as to what other federal or state grants were available for the Hallett's
component, and had we explored these possibilities first.
• There was a question on the level of private support that was being committed to our
proposal and, specifically, how much of the private donations identified for the Reiman
Gardens component was obtained from City of Ames residents.
• There was a question asked about how the community would prioritize the components of
our proposal.
It is apparent that the Vision Iowa Board is concerned about the level of funding that is being requested
in our proposal. Clearly, like the City Council, this Board is facing requests for funding that
significantly exceed the amount of funds available.
i
t
The Board seemed to believe that two of the three components of our "Connect Iowa" grant proposal fit
more appropriately in the Community Attraction& Tourism (CAT)program rather than the Vision Iowa
program for which we originally applied. It should be understood that, within the overall Vision Iowa
program, there are two funding streams administered by the 13-member Board. The CAT program is
budgeted at $12.8 million annually for each of the next three years. The Vision Iowa program received
$180 million for a one-time granting period. Only $15 million remains in this program, and several
other large projects are also vying for those dollars (Waterloo,Newton, Ottumwa, Clinton, etc.). It was
my impression that they were not enamored with our Wellness/Aquatics Complex component. As a
result of these factors, the Vision Iowa Board took the following actions:
1) Shifted our request from the Vision Iowa program to the CAT program.
2) Asked the City to prioritize the three components of our request.
3) Established a"fact-finding" sub-committee to meet with City staff to clarify the issues presented
above and to report back to the full Board by the next meeting on September 12.
I am sure you would like to know how much money will be made available for all three components of
our proposal. While I do not know for certain what this total will be, my best prediction is that we
should not expect to be offered more than $6 million for all three components. Given this total, it
is crucial that we prioritize the components so that we can make the best use of the limited funding
that could be offered us.
It is apparent that there are supporters for each of the components of our proposal and, therefore, any
prioritization of the components will upset one group of advocates. To make this task even more
difficult, staff believes that each of these components is worthy of your support and would improve the
quality of life for our citizens. To assist you in setting these priorities, I would offer the following
comments.
--It is my belief that even if all of the funds awarded by the Vision Iowa Board could be directed
towards the Wellness/Aquatics Complex, the total amount would not be sufficient to garner
enough support to pass a bond referendum for this component. The limited funds that we can
expect to receive from the CAT process will have a more significant impact on the less expensive
Reiman Garden and Hallett's Open Space components.
--Time is a crucial factor for both the Reiman Gardens and Hallett's Open Space projects. Our
purchase option with Hubbell expires on December 15, 2001. Furthermore, a companion
purchase option between Hubbell and the new owner of the quarry expires in January,
2002, and there is no guarantee that this owner will be inclined to extend the option yet
another time. Furthermore, having raised a significant portion of their project already, ISU is
poised to begin construction on the Reiman Gardens expansion. Because all work completed
prior to the approval of this state grant will not be eligible to meet the local match requirement,
ISU does not want to lose this opportunity. They would prefer to move ahead as soon as
possible.
2
--The Reiman Gardens and Hallett's components appear to have similar appeal in terms of a
regional draw for tourism and educational benefits for the state. It is, therefore, difficult to
choose between these two strong proposals.
As a result of these three factors, I would recommend that the City Council prioritize the
components of our grant proposal as follows:
First Priority—Halletts Open Space Project &Reiman Gardens Conservatory Complex
Second Priority - Wellness/Aquatics Complex
This prioritization does not signal a lack of support for the Wellness/Aquatics Complex, but
merely a realization that funding for this facility, from Vision Iowa, is not likely. In anticipation of
this reality, I would suggest that we reconsider other strategies for accomplishing this crucial project.
Issues to be addressed should include the components of the Complex, the phasing of these components,
the possibility of partnering with other entities, and the identification of other funding sources. Towards
this end, I would ask that the City Council and Parks and Recreation Commission agree to meet on
August 2 1"at 7:00 p.m. in a joint meeting to consider a new strategy for the Wellness/Aquatics project.
By prioritizing the three components of our grant proposal, it is hoped that we will increase our
likelihood of receiving some level of funding from the Vision Iowa Board and expedite their final
funding decision. Remember, in order to stay on schedule to satisfy our purchase contingencies for
the Hallett's project,we should have a bond referendum scheduled for the November election
date, with a two-month public education process prior to that date. It remains to be seen whether
the above action by the City Council will lead to a decision by the Vision Iowa Board by this
September deadline. If this can't be accomplished, then the City Council will have to decide in
early September whether to seek authorization to issue bonds in the full amount of$6.5 million,
pending a final decision of grant funding.
\sls